Re: Santa Cruz Avenue Sidewalk Project

From: domainremoved <Kirsten>
Date: Tue, 9 Feb 2016 08:03:55 -0800

Hi Betsy,

Thank you for the clarification. Justin, I would appreciate a response
regarding the road width issue that Betsy raises.

Thank you.

On Friday, February 5, 2016, Betsy Nash <nash94025_at_(domainremoved)

> Hi Justin,
>
> Just to be clear, we were not challenging existing measurements (we know
> they vary), just the staff report illustration of the proposed design,
> where two traffic lanes are shown as 11’ while the City Council approved
> plan called for 10’. Existing conditions are not represented in the
> diagram, so it seems like the design illustration should match the approved
> plan.
>
> By the way, can we get a copy of the survey – particularly the overhead
> layout property-by-property? If possible it would be great on Monday.
>
> Thanks very much!
> Betsy and Horace
>
>
> On Feb 5, 2016, at 4:40 PM, Murphy, Justin I C <JICMurphy_at_(domainremoved)
> <javascript:_e(%7B%7D,'cvml','JICMurphy_at_(domainremoved)
>
> Hello Mr. and Mrs. Nash,
>
> Thank you for your email. As part of the presentation on Tuesday night,
> staff will provide a clarification of the measurements with some visuals.
> In general, the travel lanes are between 10 feet and 11 feet from center
> line of stripe to center line of stripe. The study session will provide a
> good forum to confirm Council direction and intent going forward.
>
> Sincerely,
> Justin Murphy
> Public Works Director
>
> -----Original Message-----
> From: Betsy Nash [mailto:nash94025_at_(domainremoved)
> <javascript:_e(%7B%7D,'cvml','nash94025_at_(domainremoved)
> Sent: Thursday, February 04, 2016 10:41 PM
> To: _CCIN
> Subject: Santa Cruz Avenue Sidewalk Project
>
> Dear Council and City Manager,
>
> Staff Report Number 16-031-CC for Tuesday 2/9 meeting includes a BKF
> street design plan that erroneously uses 11-foot travel lanes rather than
> the Council-approved 10-foot travel lanes. See attached excerpts. This
> 2-foot difference undoubtedly affects the evaluation of drainage issues.
> In any event, please ensure that the Council-approved dimensions are used
> in future planning.
>
> Thank you,
> Betsy and Horace Nash
>
>
>
Received on Tue Feb 09 2016 - 08:08:11 PST